英语简答题
1个回答
展开全部
1 WPS
2 The project manager controls whole resources and progress of the project including but not limit to the cost, quality, schedule, safety and HR, money, etc.
3 Site handover after signing the Contract.
4 No. The contractor has to take all responsiblities of any loss and additional possible losses caused by it's error and delay.
5 The contractor should implement the determination without delay, at the same time it can write a letter to the employer to express it's concern and claim. The employer should study the letter and deliver it's definite opinion to the contractor till the two parties reach an agreement for the determination.
6 Materials cost. Other cost components are also very important.
7 Different stages of the project development have respective specialties so the cost components are not same as stages changing.
8 The contractor.
2 The project manager controls whole resources and progress of the project including but not limit to the cost, quality, schedule, safety and HR, money, etc.
3 Site handover after signing the Contract.
4 No. The contractor has to take all responsiblities of any loss and additional possible losses caused by it's error and delay.
5 The contractor should implement the determination without delay, at the same time it can write a letter to the employer to express it's concern and claim. The employer should study the letter and deliver it's definite opinion to the contractor till the two parties reach an agreement for the determination.
6 Materials cost. Other cost components are also very important.
7 Different stages of the project development have respective specialties so the cost components are not same as stages changing.
8 The contractor.