model:
sets:
warehouse/1..2/:ownership2;
factory/1..2/:ttime;
item/1..5/:demand3;
material/1..3/:;
production/1..2/:;
link1(material,warehouse):ownership1;
link2(production,material):expend;
link3(factory,production):time,cost,produce,ability;
link4(item,production):demand1;
link5(item,material):demand2;
link6(factory,item):transportcost1;
link7(factory,item,production):transport1;
link8(warehouse,factory):transportcost2;
link9(warehouse,factory,material):transport2;
link10(warehouse,item):transportcost3,transport3;
link11(warehouse,item,material):transport4;
endsets
data:
ownership1=
5000 7000
5500 6500
10000 6000;
ownership2=380 450;
expend=
9 13 23
11 15 20;
time=
30 40
40 35;
ttime=20000 10000;
ability=
120 80
100 120;
cost=
320 300
280 360;
demand1=
80 0
100 90
100 60
60 50
30 120;
demand2=
50 30 40
0 120 100
70 120 160
40 90 30
60 90 40;
demand3=140 120 100 220 70;
transportcost1=
20 40 100 50 40
40 50 120 70 60;
transportcost2=
90 50
60 40;
transportcost3=
10 10 20 30 20
10 15 15 5 30;
enddata
min=@sum(link11(i,k,m):transport4(i,k,m)*transportcost3(i,k))
+@sum(link10(i,k):transport3(i,k)*transportcost3(i,k))
+@sum(link9(i,j,m):transport2(i,j,m)*transportcost2(i,j))
+@sum(link7(j,k,n):transport1(j,k,n)*transportcost1(j,k))
+@sum(link3(j,n):produce(j,n)*cost(j,n)+@if(produce(j,n)#gt#ability(j,n),200*(produce(j,n)-ability(j,n)),0));
@for(factory(j):@for(material(m):@sum(warehouse(i):transport2(i,j,m))=@sum(production(n):produce(j,n)*expend(n,m))));
@for(production(n):@for(factory(j):@sum(item(k):transport1(j,k,n))=produce(j,n)));
@for(warehouse(i):@sum(item(k):transport3(i,k))<=ownership2(i));
@for(warehouse(i):@for(material(m):@sum(item(k):transport4(i,k,m))+@sum(factory(j):transport2(i,j,m))<=ownership1(m,i)));
@for(factory(i):@sum(production(n):produce(i,n)*time(i,n))<=ttime(i));
@for(item(k):@for(production(n):@sum(factory(j):transport1(j,k,n))=demand1(k,n)));
@for(item(k):@for(material(m):@sum(warehouse(i):transport4(i,k,m))=demand2(k,m)));
@for(item(k):@sum(warehouse(i):transport3(i,k))=demand3(k));
end

data部分自己按你的数据改一下就行了
来自:求助得到的回答
推荐律师服务: 若未解决您的问题,请您详细描述您的问题,通过百度律临进行免费专业咨询

为你推荐:

下载百度知道APP,抢鲜体验
使用百度知道APP,立即抢鲜体验。你的手机镜头里或许有别人想知道的答案。
扫描二维码下载
×

类别

我们会通过消息、邮箱等方式尽快将举报结果通知您。

说明

0/200

提交
取消

辅 助

模 式