关于一道成本会计的题目
Acompanyusesabsorptioncostingwithapredeterminedhourlyoverheadabsorptionrate.Thefollow...
A company uses absorption costing with a predetermined hourly overhead absorption rate. The following situations arose last month:
(i) Actual hours worked exceeded planned hours.
(ii) Actual overhead expenditure exceeded planned expenditure.
Which of the following statements is correct
A Situation (i) would cause overheads to be over absorbed and situation (ii) would cause overheads to be under absorbed.
B Situation (i) would cause overheads to be under absorbed and situation (ii) would cause overheads to be over absorbed.
C Both situations would cause overheads to be over absorbed.
D Both situations would cause overheads to be under absorbed.
答案是A为什么 展开
(i) Actual hours worked exceeded planned hours.
(ii) Actual overhead expenditure exceeded planned expenditure.
Which of the following statements is correct
A Situation (i) would cause overheads to be over absorbed and situation (ii) would cause overheads to be under absorbed.
B Situation (i) would cause overheads to be under absorbed and situation (ii) would cause overheads to be over absorbed.
C Both situations would cause overheads to be over absorbed.
D Both situations would cause overheads to be under absorbed.
答案是A为什么 展开